Yea you're right
I know you are just trying to protect your hand in that there SNC pocket,
I mean anyone can clearly see how every public transit project costs 4 to 6x its original and thats is OK - someones getting some cushion. hah.
Since you must know - got a link to the budget or even a spreadsheet - at to how the costs were derived?
And how about some documents showing how the longterm lease price of the 407 was computed?
Sorry, I've got not involvement in the UP project, nor do I, nor have I ever been involved with SNC Lavalin. (Who originally were going to design, build, finance the project in what has become affectionately known as P3 partnerships, which seldom work. When the SNC daydream fell apart, the entire project was mandated to Metrolinx to complete and bring to fruition.)
You make me laugh because you are woefully ignorant of how infrastructure is built and like so many other ignorant people think that "the politicians" are to blame and somehow there is graft or corruption in there.
Let me give you the Coles Notes version of how public infrastructure is built in Canada and Ontario and Toronto.
1. The politicians come up with a want (maybe it's a new subway, or LRT, or it's a railway to the airport)
2. Purchasing will put out a Request for Proposals to qualified Engineering Consultants (like SNC, or AECOM, or Hatch, or AMEC, or any number of firms.) to do a "study" for discussion purposes. At this time, some very preliminary budgets are conjured up. Unfortunately, fools often think that this is what it should cost and fools will bray away about infrastructure projects being 4 times over budget because they use the initial budgets that were based on no design whatsoever to say that everything is over budget by 400 percent.
3. Next step is the Environmental Assessment. Again, invite qualified firms, or publically tender, but again the lowest bidder is selected to do the work. The Environmental Assessment takes forever and it does exactly what its name implies - looks at the impacts to the environment and establishes the criteria that the final design must have. At this time, there are usually several alternative designs concepts (not detailed design) drawn up and again, cost estimates are put together.
5. Next step is Preliminary Design. Again, invite qualified firms, or publically tender, but again, lowest bidder is selected. A preferred design will be selected and again project costs are estimated, this time with some greater accuracy, but in no way completely accurate.
6. Next step is Detailed Design producing tender drawings and specs suitable for tendering to construction by qualified Contractors. Again, lowest bidder is selected. (There is no second prize by the way.) At this time, a final design is detailed. It can be thousands of drawings and a spec a metre thick. At this time, an Engineer's cost estimate will be put together. A good Engineer will put together a cost estimate that should rank him Number 2 or 3 when the construction tenders come in.
7. Tender for Construction. Again, low bid gets the job. Prices should be equal or less than the Engineer's estimate done in step 6, but often times they are actually higher because Contractors know more about pricing a job than Engineers. This should be "THE BUDGET" for the job, not the budget that was arrived at in stage 1 which fools always get hung up on.
8. Construction proceeds and yes, there are ALWAYS extra costs. The question is how much extra. If you have a damn good Engineer in Step 6, and I mean DAMN GOOD (and they are out there, but unfortunately, they are usually not the lowest bid), your final construction cost should be within 10 percent of your budget. If you have a design that is full of holes and mistakes, the sky is the limit in terms of extra costs.
So through it all mon ami, the lowest bid gets the job.
So tell me, please, enlighten me, as to how the politicians are somehow responsible for cost over runs?
Everything and I mean everything is publically tendered with low bid getting the job. Politicians do not hand out contracts to their buddies despite public perception to the contrary.
All of the above can take years, even decades and the reason it takes so long is that because the public has to be consulted at ever step of the process and that takes time.