Keebler Elf said:
I think you're wrong on both counts.
The province may very well love to give up the 401 and all its associated maintenance costs. They gave the Gardner to Toronto and it's been nothing but a headache.
How do you figure the bigger cost is the stations? It's extremely expensive to tunnel...
Cause I have a knowledge of construction and the construction of Sheppard that you do not. I am in fact, correct on both counts.
The cost of the Sheppard was just under a billion dollars for about 6 km of track.
The contract to tunnel bore was awarded to S. McNally of Hamilton Ontario for just under 100 million dollars.
http://www.mcnallycorp.com/project_profile.php?id=33&action=project_feature
The cost of the line is ALWAYS the stations mon ami. The Yonge Sheppard Station clocked in at 130 million buckeroos. Even the cheapest station on Sheppard - Bessarian was around 30 million bucks.
Stations, especially Yonge where the lines cross, is very complex, requiring virtual relocation of every utility under the intersection at huge costs.
The province will never give up the 401 corridor for an LRT. The Gardiner was a different story because basically it just is the Toronto end of the QEW. The 401 goes right through. Also, the province only gave, (or more accurately forced) the ownership of the portion of the QEW from 427 to the Humber which used to be QEW. The main portion of the Gardiner (from the Humber to the DVP) has always been the property of the City of Toronto.
A far far far better route for an LRT would be the CPR North Toronto Subdivision which runs east / west from Leaside Yard at Millwood to Toronto West Junction at Keele and Dundas. This line passes right through uptown(the old CPR Summerhill Station for example which is now the famous liquor Store.)
You could have commuter stations at Davenport, Spadina, Bathurst, Dufferin and Keele.
The existing track corridor is currently fitted for 5 tracks, with room for 6.
There are only 2 tracks currently being used, though there are also sidings starting at Davenport, running westwards to Shaw Street. Still there is more than ample room on the south side of the corridor where you could easily construct 2 commuter lines utilizing the former Ontario Quebec Railway's right of way (which CPR now owns).
East of Leaside, the CPR follows the Belleville Subdivision, which is ABANDONNED south of Leaside yard all the way down to UNION Station. That big monster of a bridge you see across the ramp from Danforth to the DVP hasn't been used in years.
You could easily and perfectly run LRT from Union Station north to the CPR's Leaside yard where you could then run east / west all the way to Keele and Dundas, where you could hook into the Galt Subdivision that runs to Georgetown. (GO Transit currently owns the Galt subdivision from Union Station running northwest to Toronto West Junction at Keele and Dundas.)
All you need to do is come up with a deal with CPR.