Average time for a Toronto skyscraper to be built after approval?

black booty lover

Well-known member
Oct 21, 2007
9,769
1,751
113
I know there a lot of smart Terbites on here so I thought this would be a good place to pick a few smart brains. With Toronto's ever growing skyline, I was checking out these proposed supertalls (skyscrapers that reach a height of 300 meters or higher) and there are currently 5 proposals that qualify as supertalls with one development falling just shy by 1 meter:


I realize there are a tone of variables as to when and even if they get built, but I was curious to know if there is some sort of general time frame most get built in. For example, the link I posted above, a few of the proposals are from back in 2012. Also, some have already been approved and some have just been proposed.

I'm just curious cause I'm kind of excited to see what the skyline would like, and if I'll still be alive for it...lol.
 
  • Wow
Reactions: luvyeah
So many variables - finance one of the largest. Once all is a go - depending in the hole in the ground (1/2 years) - once out of the ground basically a floor a week from there.
 
  • Like
Reactions: The Fruity Hare
So many variables - finance one of the largest. Once all is a go - depending in the hole in the ground (1/2 years) - once out of the ground basically a floor a week from there.


What kind of finance? They have to prove they tenants and that sort of thing?
 
Do you have any idea how many water bottles 🍼 full of piss there are in the walls behind the drywall in these skyscrapers? I've been on 3 floor jobs where guys won't walk to use the portable pisser.
 
  • Like
Reactions: nervousintheservice
I know there a lot of smart Terbites on here so I thought this would be a good place to pick a few smart brains. With Toronto's ever growing skyline, I was checking out these proposed supertalls (skyscrapers that reach a height of 300 meters or higher) and there are currently 5 proposals that qualify as supertalls with one development falling just shy by 1 meter:


I realize there are a tone of variables as to when and even if they get built, but I was curious to know if there is some sort of general time frame most get built in. For example, the link I posted above, a few of the proposals are from back in 2012. Also, some have already been approved and some have just been proposed.

I'm just curious cause I'm kind of excited to see what the skyline would like, and if I'll still be alive for it...lol.

In most cases projects I have been involved in depend on a few variables that control the speed of a building going up. The most important is the financing. The second most important is the Architectual/Structural design team. If the designs are incomplete a simple building could take years to complete due to rfi’s and design build changes. The sub contractor
submits a rfi on a design, the design team review the rfi and. Revise the designs, the sub then submits quote for design change and it is reviewed and approved then design dwgs are revised and new material acquired ( this process can take months)..I have worked on many projects that have gone up fast and many that have taken years and to determine the speed of a building all depends on the quality of the designs of the project...The actual build phase takes very little time once the direction is established.
 
I know there a lot of smart Terbites on here so I thought this would be a good place to pick a few smart brains. With Toronto's ever growing skyline, I was checking out these proposed supertalls (skyscrapers that reach a height of 300 meters or higher) and there are currently 5 proposals that qualify as supertalls with one development falling just shy by 1 meter:


I realize there are a tone of variables as to when and even if they get built, but I was curious to know if there is some sort of general time frame most get built in. For example, the link I posted above, a few of the proposals are from back in 2012. Also, some have already been approved and some have just been proposed.

I'm just curious cause I'm kind of excited to see what the skyline would like, and if I'll still be alive for it...lol.
2-4 years once they break ground
 
In most cases projects I have been involved in depend on a few variables that control the speed of a building going up. The most important is the financing. The second most important is the Architectual/Structural design team. If the designs are incomplete a simple building could take years to complete due to rfi’s and design build changes. The sub contractor
submits a rfi on a design, the design team review the rfi and. Revise the designs, the sub then submits quote for design change and it is reviewed and approved then design dwgs are revised and new material acquired ( this process can take months)..I have worked on many projects that have gone up fast and many that have taken years and to determine the speed of a building all depends on the quality of the designs of the project...The actual build phase takes very little time once the direction is established.


Yeah I think that's sort of what I was trying to figure out because I can see once a building is started, it doesn't take that long. It's everything up to that point that I didn't really understand. In the link I provided, a few of the buildings submitted their proposals back in 2012, but there is a new skyscraper going up at 212 King street that's supposed to break ground in early 2022 but just submitted their proposal in the last few months so it was kind of confusing.
 
Do you have any idea how many water bottles 🍼 full of piss there are in the walls behind the drywall in these skyscrapers? I've been on 3 floor jobs where guys won't walk to use the portable pisser.

That and so much more :). Zip ties to hold pipes - etc. Some crazy stuff that should not be permitted.

What kind of finance? They have to prove they tenants and that sort of thing?

For the Financing - they have to have XX amount pre-sold usually 75%. Then the Developer gets draws to pay for different stages - investment Co’s don’t give up all the dough ahead of time.
 
  • Like
Reactions: RichardG2020
That and so much more :). Zip ties to hold pipes - etc. Some crazy stuff that should not be permitted.



For the Financing - they have to have XX amount pre-sold usually 75%. Then the Developer gets draws to pay for different stages - investment Co’s don’t give up all the dough ahead of time.

It would only be buyer if it's condos no?? If it's an office tenants are leasing the space no??
 
It would only be buyer if it's condos no?? If it's an office tenants are leasing the space no??
Absolutely , I have not seen new office towers in the core for a while - mixed use - office first - 5/7 floors then Condo or Residential Rental.
I believe with Covid you will see some office towers converted to Condo / Apt Rental.
 
Absolutely , I have not seen new office towers in the core for a while - mixed use - office first - 5/7 floors then Condo or Residential Rental.
I believe with Covid you will see some office towers converted to Condo / Apt Rental.

I think the attempt to create an "office condo" market in Toronto in those various Yonge St. Projects is about to fail.
 
I think the attempt to create an "office condo" market in Toronto in those various Yonge St. Projects is about to fail.
Short term blip with Condos (well in the long game). Covid has thrown a curve ball at the World. The Office Towers will have significantly reduced Commercial tenants and others playing a long term game with dough will turn Office towers into mixed use. A normal year - 300,000 plus move to Canada - 75% stay in TO. That won’t go away permanently.