Bloor-Danforth line reopens after 7-hour shut down

Metrolinx was supposed to fix the problem they created but failed to do so , then mud and water gave way and flooded the tracks. There was no service problem until the earth gave away over time, a driver called in the problem and they suspended service. Metrolinx is going to be a very unreliable provider with problem solving like this.
 
I'd just like to know what the engineers were thinking when they planned this construction project. Obviously, they weren't thinking about it enough.
 
Metrolinx is simply the owner. Tough to blame them directly. (Though as owner, they would be responsible to TTC and then Metrolinx would go after the General Contractor / Engineer (big time) that was doing the work.

Aplus General Contracting is building the GO Station at Bloor, just east of Dundas West. They were the ones driving the piles (well, most likely it was a subcontractor), not Metrolinx. (Thoiugh Aplus is working for Metrolinx.).

An investigation will need to be done.

There are a couple of possibilities.

1. The actual position of the subway tunnel and what was shown on the contract drawings that Aplus is using were not correct.

2. The pile driver working for Aplus did not properly locate or drive his piles correctly given the location of the tunnel.


So it could go either way - it could be the pile driver's fault, or it could be whoever designed the new GO Station's fault

Too bad someone didn't think to do a proper total station survey BEFORE they started banging piles into the ground. But hind sight is always 20 20.


BTW, really stupid to drive piles so close to a tunnel, even if you had figured you would miss the tunnel. When you drive piles, you create A LOT of pressure in the soil adjacent to the pile and you can easily blow out a tunnel.
 
I'd just like to know what the engineers were thinking when they planned this construction project. Obviously, they weren't thinking about it enough.

Could be that the pile driver drove the pile in the wrong place, or got the angle on the pile wrong.