This is just early finish for the current contract.
Next contract for rehab of section for Humber River out to 427 is already starting with rehab of overpass bridges
Then it will be roadway sub grade repairs, guard rail swap to concrete barriers, new roadway lighting, etc.
So that will go for 3-4 years.
At work we bid on the next design phase, which I recall was from around Yonge to Pricess Gates area.
It was to determine what needed to be done and specify it so the actual works and detailed design for them can ne tendered as a design-build contract.
We lost that bid, but not upset because there was still a lot of fiscal risk in the works.
Then there is design going on for rebuild of ramps from DVP to Gardiner. About Cherry to the railway track crossing.
Again we bed and were not sucessful ,and again lots of design risk.
So rehab for the Gardiner will be ongoing in one form or other for at least the next decade.